Key project milestones
Strategic Outline Business Case submission
July 2019The project partners (North Somerset Council and Somerset County Council) submitted a Strategic Outline Business Case (SOBC) for the A38 route improvements to central Government in July 2019. This document set out the broad case for change along the route and highlighted potential locations for improvement.
Public consultation
Monday 21st June 2021 to 23:59 on Sunday 1st August 2021People and businesses are invited to have their say on a series of proposed improvements along the stretch of the A38 running from the South Bristol Link to Edithmead Roundabout.
Outline Business Case submission
Autumn 2021We intend to submit the Outline Business Case for the A38 Major Road Network improvements to central Government in Autumn 2021.
Secure necessary consents
Spring 2022If the Outline Business Case is successful, we will look to secure all necessary consents to start the work by Spring 2022.
Full Business Case submission
Summer 2022We will submit the Full Business Case in Summer 2022 to secure sign-off on the funding, which is likely to take 3 months.
Construction phase
October 2023 onwardsAfter funding is secured, we intend to commence construction in October 2023.
Construction complete
Autumn 2025If all goes to plan, the route improvements will be fully open and operational by Autumn 2025.
What would you like to do?
Key information
This consultation runs from Monday 21st June 2021 to Sunday 1st August 2021 at 23:59.If you have any questions or queries about the A38 Major Road Network project or this engagement process, please get in contact or email the project team at hello@a38mrn-engagement.com.